The research project Arctida presented an analysis of 15 major industrial and infrastructure projects in the Russian Arctic on November 10. The authors examine the developments as an interconnected system in which resource extraction, energy, transport and government financing depend on one another. They conclude that the environmental and traditional land-use impacts of individual facilities cannot be assessed solely within the boundaries of each construction project.
The sample covers oil and gas developments and other resource projects, the Northern Sea Route, railway infrastructure, nuclear energy and ship repair. The researchers compared government and corporate documents, environmental impact assessments, public consultation records and investment plans.
Among the examples is Yamal LNG, whose infrastructure, the study says, affects traditional reindeer-herding routes. The authors also note that public documentation for several projects in Murmansk region does not adequately identify the Sámi as a distinct affected community. They argue that the cumulative impact of several connected developments on land and local communities may exceed the effects assessed for each project individually.
The Northern Latitudinal Railway is presented as an example of repeatedly revised plans. Its scheduled opening was pushed from 2019 to 2023 and then to 2027–2031; the concession project was suspended in late 2025. Cost estimates in successive versions rose from 122 billion rubles to more than 800 billion rubles. Those figures came from different planning stages and do not represent two simultaneously current budgets.
Another example is Arctic LNG 2, where sanctions have disrupted the original export model, according to the authors, despite the commissioning of the first production train. The researchers argue that sanctions have increased Arctic projects' reliance on the state and state-owned banks while forcing revisions to logistics, ownership structures and technology procurement.