The Moscow Times examined government registers and counted at least 294 federal construction projects whose completion deadlines had been postponed. The outlet calculated their combined cost at approximately 9.5 trillion rubles. Construction has not even begun on another 382 planned projects worth at least 1 trillion rubles.
The study covered 1,238 federal capital construction projects and departmental programs. Of these, 402 had been completed and another 160 were proceeding on schedule at the time of the study. Those 160 projects were still under construction; they had not already been delivered on time.
The delayed projects identified by journalists included a gas processing complex in Ust-Luga worth about 3.5 trillion rubles, the Northern Latitudinal Railway and the Kursk Nuclear Power Plant's second phase. The outlet also calculated that deadlines had been postponed for 128 transport projects worth more than 3.4 trillion rubles and 43 hospitals and dispensaries costing approximately 438.5 billion rubles in total.
The investigation also described the practical consequences. The opening of the Krasnoyarsk light-rail system was postponed from 2026 to 2029, while delayed healthcare projects include oncology centers in Stavropol, Sevastopol and Nalchik. The number of reported deadline extensions rose from 15 in 2021 to 86 in 2025, with another 81 recorded during the incomplete year of 2026.
Authorities most often cite insufficient funding, and less frequently equipment shortages. These are postponements recorded in official programs, not formal decisions to cancel all the projects permanently.